The D365 Finance Cutover Rehearsal Playbook: The 2 Dry Runs That Save Your Go-Live

The D365 Finance Cutover Rehearsal Playbook: The 2 Dry Runs That Save Your Go-Live

If a D365 Finance go-live fails, the root cause is rarely “the system.” It’s usually cutover discipline: unclear owners, missing timings, no rollback, and no throughput data. Here’s the two-rehearsal playbook I use to prevent that.

Outcome: two full dress rehearsals with measured timings, clear RACI, signed acceptance criteria, and a rollback you’ve actually tested.


Why most cutovers fail (and how to avoid it)

  • No named owners per domain → fix with a RACI and sign-off points.
  • Scope creep on history → freeze decisions early in a log.
  • One token dry run → do two rehearsals with full volumes.
  • No throughput metrics → measure every step (mins, records/min, error%).

The Playbook Overview

  • Rehearsal #1 (T-6 to T-4 weeks): full-volume import with known defects allowed, objective is timings + bottlenecks.
  • Rehearsal #2 (T-2 weeks): full-volume import with go/no-go criteria (quality + timings). This is your go-live rehearsal.

RACI for cutover (core roles)

Area / Step Owner (A/R) Support (C/I) Acceptance
Freeze transactions (code freeze window) PMO (A) IT Ops, Business Leads (C) PMO + Sponsor
Master data final delta (Vendors/Customers/Items/Projects) Business Leads (A) Data Team (R), SI (C) Domain Lead
Open items (AP/AR/Bank/Projects) Business Leads (A) Data Team (R) Finance Director
GL opening balances Finance Controller (A) Data Team (R) Controller + Auditor (if req.)
Security roles toggle (pre-go-live) IT Security (A) SI (C) PMO
Smoke tests & sign-off Process Owners (A) Key Users (R), SI (C) PMO + Sponsor

(A=Accountable, R=Responsible, C=Consulted, I=Informed)


Rehearsal #1 — timings & bottlenecks

Goal: benchmark duration + throughput and surface blockers.

Scope checklist

  • Full volumes for: Vendors, Customers, Items, Projects, opening balances, open AP/AR/bank, project WIP as applicable.
  • “Happy path” smoke tests only (posting profiles, dimension entry, tax calc, vendor payment proposal, bank recon import).

What to capture (minimum)

Step Target Owner Actual Notes
Export freeze starts 19:00 PMO
Master delta import 40 min Data Team Records/min
Open AP/AR load 30 min AP/AR Lead Errors?
Opening GL load 20 min Controller Balances tie-out?
Security switch 10 min IT Sec
Smoke tests 45 min Process Owners Pass/Fail

Deliverables: a one-page timing sheet, a list of bottlenecks with owners, and revised targets.


Rehearsal #2 — go/no-go criteria

Goal: prove the go-live is repeatable, within time, and reversible.

Pass criteria (example)

  • All imports within ±10% of targets from Rehearsal #1 (after optimizations).
  • Error rate ≤ 0.5% across master & open items (known exceptions listed).
  • End-to-end duration ≤ 6 hours (fits your window).
  • Rollback tested: one import intentionally fails; team executes rollback and re-run within 45 minutes.

Sign-offs required

  • AP, AR, GL, Projects each sign “numbers reconcile” against legacy/source.
  • PMO signs “cutover book” with timings, owners, acceptance checkpoints.

The war-room (minute-by-minute)

  • Single channel (Teams/Slack) with pinned run-sheet + decision log.
  • Timekeeper calls each step start/finish; posts timestamps.
  • Red/Amber/Green board for each workstream; only PMO can change status.
  • Decision log lines: Decision, Impact, Owner, Time, Reversal Path.

Rollback policy (you must test it)

  • Define rollback triggers (e.g., error > X%, duration > target + Y minutes).
  • For each step, specify reversal (delete batch, restore backup, revert security).
  • Assign rollback captain separate from the step owner.

Common pitfalls & quick fixes

  • “Data” as one line item → split by domain and name the owner.
  • Late change to scope/history → push to data warehouse, not ERP.
  • Under-estimating security → rehearse role toggles and approvals.
  • No clock → appoint a timekeeper and publish a wall clock in the channel.

Copy/paste mini-checklist

  • [ ] Owners + RACI named and briefed
  • [ ] Decision log template ready
  • [ ] Two rehearsals scheduled (T-6/T-4 and T-2)
  • [ ] Timing sheet prepared + throughput targets set
  • [ ] Rollback steps written and tested
  • [ ] Smoke tests list agreed + acceptance criteria signed